Cummins CFP15 Hydraulic start systems

Qatar’s New LPG Bottling Facility
A new liquefied petroleum gas (LPG) bottling plant is under construction in Ras Laffan. The contractor appointed for this state-of-the-art facility is focused on enhancing LPG supply resiliency in Qatar. As a sub-contractor Hatraco has been awarded an order for the delivery of 2x hydraulic start systems to provide backup start energy for Cummins CFP15 driven Fire water pumps.  

As per NFPA-20 requirements for a secondary start system, the start system provides the minimum of 6 times of 15 seconds of start duration. By means of pre-set pressure values, the hydraulic start system is automatically recharged by means of an electric motor driven recharge pump. The recharging cycle is managed by pressure transmitters in combination with a local control panel.


 

TECHNICAL INFORMATION
Project:LPG bottling, Ras Laffan
End user:Qatar energy
Location:Ras Laffan inductrial city, Qatar
EPCC:Roots Energy & Engineering Services / Black cat engineering
Start capacity:3 x 50 Litres
Start requirements :6 times, 15 seconds each
Recharge time:within 30 minutes
Engine:Cummins CFP 15
Required engine firing speed  :110 - 120 RPM
Application:Cummins CFP 15 diesel engine driven fire water pump
Design code / Certification   :Accumulator design according to ASME VIII Div 1, U stamped
Specialties:1 start valve manifold for accumulator depletion
  Local control panel